Home | Contact Us | PIP Careers  
 Cost reduction - coal

Context / Scope of project

An open cast coal mine was suffering from a margin squeeze as a result of the Global Financial Crisis - costs had risen during a period of escalating prices and “increasing production at all costs” and then coking coal prices dropped 60%. PIP worked with the management in a short diagnostic to identify savings.

A number of control and wiring issues on site were apparent:

  • There was no control of access to site
  • Cost information was difficult to access
  • Spend was initiated without authorisation resulting in erratic and escalating expenditure and inaccurate accruals
  • The procure-to-pay process was not functioning effectively with unmatched invoices representing half the monthly costs ($35m)
  • Cost Review Meetings were aimed at trying to allocate costs correctly not at problem solving how to reduce costs.

At the end of this diagnostic a target of $134m of cost savings (16% of total costs) was agreed. A four-month engagement was then started; this was extended by 2 months with a smaller team.

Cost per tonne had more than doubled over the last 5 years, with contractor costs being the largest contributor to this

Client achieved: (completed in 6 months)

  • Developed a pipeline of $180m of improvement ideas of which $143m were fully evaluated and in Implementing + Cash Flowing + Locked-in statuses
  • Reduced actual cash cost by 13%
  • Improved competitiveness as a world coking coal supplier, and re-entered list of lower quartile coking coal producers
  • Negotiated a 3% reduction in prices with suppliers
  • Reduced usage of on-site contractors by $8m / year
  • Eliminated work that unnecessarily built up inventory of pre-strip
  • Consolidated labour on site
  • Implemented a procure-to-pay process and recipient created tax invoices.

graph


graph


graph


graph


graph


graph

 

 

Back to top  |  Back to 'Our Results' page     


Back to 'Our Clients' Results'
  

What we did:

  • Created teams in each area with specific targets (Mining, Maintenance, Coal Handling Prep Plant (CHPP), and Commercial). Later, separate streams were created for negotiating Price Reductions, and implementing Procure-to-pay improvements
  • Each stream prepared Value Driver Trees, identified opportunities, held Idea Generation Sessions, prioritised ideas and then progressed these ideas through the Ideas Pipeline
  • A pipeline worth $180m was created

  • Commercial
  • Initially addressed the usage lever by introducing a weekly “Spend SPIN” cycle to ensure pre-planned authorisation of contractor services on site and controlled management of them once on site and in the invoicing/payment processes
  • Then, addressed the price lever, by setting up a Rapid Sourcing Stream to identify opportunity for negotiated price reductions and set up negotiations with selected suppliers to reduce prices, by taking advantage of the GFC (Global Financial Crisis)
  • Renegotiated prices and terms with labour and consumables suppliers.

  • Mining
  • Created a tool to assist Supervisors plan their truck allocation based on the relative operating costs, capacities and distances to relative pits.
  • Reduced equipment on hire e.g. loaders, dozers
  • Stopped draglines uncovering coal, and used dozers instead to reduce losses in uncovering coal
  • Postponed removal of pre-strip to maintain stocks and improve cash flow.
  • Maintenance
  • Introduced condition monitoring to predict failure and initiate repair or replacement of components
  • Allocated cost of damage to the department that caused the damage; this was especially effective with Dragline operations and resulted in Superintendent taking responsibility for reducing damage
  • Reduced number of contract staff and changed the service provider
  • Created a project plan to implement maintenance schedules that had lapsed.

  • CHPP
  • Consolidated Maintenance contractors
  • Changed contractor schedules to tie in with scheduled shutdowns minimising idle time.

  • Wiring
  • Reduced maximum limits for all authorisers of purchase and stores requisitions
  • Raised authorisation of overtime to Superintendent level
  • Established individual RARs (Results Action Reviews) between the EGM and his Managers to improve the focus, improvement pipeline and the quality of decision making around costs
  • Established a Cost Review chaired by the EGM so that the costs in each department were interrogated
  • Established Idea Owner Reviews to track the progress of ideas
  • Implemented a rigorous procure-to-pay process ensuring that all expenditure would be authorised prior to making commitments, so that accruals could be made more accurately
  • Implemented Recipient Created Tax Invoices in Commercial to improve the accuracy of invoicing, reduce invoice processing time and activities.

  • Coaching
  • Trained improvement team and line managers in Continuous Improvement tools and skills including Idea Owner Reviews, RARs, Cost Reviews
  • Trained all users in procure-to-pay
  • Coached Commercial department and Operations Superintendents and Managers in Negotiation Skills.

 


 
  ©Copyright Partners in Performance 2004 | Disclaimer